  • Survey and studies (completed)

    February-May 2022
  • Preliminary design (completed)

    March-July 2022
  • Design open house

    August 2022

    You are here

  • Final design

    September-December 2022
  • Right-of-way acquisition

    October 2022-July 2023
  • Contractor bid process

    August 2023
  • Construction begins

    October 2023
  • Project completion

    February 2024