This open house was active from Aug. 5-20, 2022. Information on this website may no longer be current. Email us for more information.
Dates subject to change.
-
Survey and studies (completed)
February-May 2022
-
Preliminary design (completed)
March-July 2022
-
Design open house
August 2022
You are here
-
Final design
September-December 2022
-
Right-of-way acquisition
October 2022-July 2023
-
Contractor bid process
August 2023
-
Construction begins
October 2023
-
Project completion
February 2024